What are the key facts in brief (TL;DR)?
- On 13 November 2026, Siemens Mobility handed over the 294th Desiro ML to ÖBB at Vienna Central Station, completing the largest train procurement programme in ÖBB history. All 294 sets were delivered on time; 273 were built in Austria with ÖBB TS.
- 294 is the total fleet size of the programme, not a separate order or an unexercised option. The last call-off of 21 trains in April 2024 raised the fleet from 273 to 294, and every unit in that number is now delivered.
- The ETCS retrofit is officially scheduled for completion in 2028, but Siemens and ÖBB do not publish the baseline, the on-board supplier or the retrofit contractor. An earlier public target was the end of 2023.
- The retrofit is not a “signal spare parts” programme. It is an on-board signalling and software modification, with interfaces to braking, traction, doors and the driver desk. Spare parts are the support inventory that follows approval of the modified vehicle.
- For maintenance and procurement teams, fleet completion fixes the configuration baseline. Parts must now be matched to a build standard and an ETCS software state, not just to a train number. Our spare-parts guides set out how that matching works for Siemens, Bently Nevada and other platforms.
Ten years of deliveries ended at a platform in Vienna, not in a factory. That detail matters: the handover closes the build phase and opens a sustainment phase in which the same 294 trains will carry two major changes — a fleet-wide ETCS retrofit and the reopening of the rebuilt Vienna S-Bahn core line.
What exactly did Siemens hand over on 13 November 2026?
Siemens handed over the 294th and final Desiro ML electric multiple unit to ÖBB at Vienna Central Station on 13 November 2026, closing the procurement programme. All 294 sets were delivered on time, and 273 of them were built in Austria under the ÖBB TS–Siemens Mobility manufacturing partnership.
- More than one million production hours went into 898 individual rail carriages, according to Siemens Mobility, 13 November 2026.
- The fleet operates in configurations from 75 m to more than 101 m in length; the same release confirms that all 294 trains are in service as Cityjets.
- The handover took place at Vienna Central Station. Siemens’ German-language release, carried by OTS on 13 November 2026, names the same location and date.
The number is a fleet count, not a delivery sequence in isolation. ÖBB’s largest commuter and regional fleet is now complete, and no further Desiro ML units are on order under this programme.
Does 294 mean the contract total, the accepted units, or a number that includes options?
294 is the total fleet size of the Desiro ML programme, not a separate order and not an unexercised option. The final call-off of 21 trains in April 2024 raised the fleet from 273 to 294, and Siemens has now delivered every unit in that number.
- The programme began with a 2010 tender that Siemens won. The original framework covered 200 trains and was completed when the last 11 were called off in January 2020, as Siemens Mobility reported on 31 January 2020.
- The April 2024 order for 21 additional sets stated that the fleet would grow to 294, with 236 already in service at that point: Siemens Mobility, 29 April 2024.
- ÖBB’s fleet overview lists 274 sets in stock, including 46 four-car sets and 27 three-car sets for Interregio services. That page is not date-stamped and appears to be a snapshot taken before the final handovers, so it should not be read as the programme total: ÖBB Konzern, fleet overview.
The sequence is therefore: 101 sets in service from 2015, 64 called off in 2016, 24 in 2019, 11 in 2020 to complete the 200-train framework, further call-offs that took the fleet to 273, and 21 more in 2024 to reach 294. The “294th train” is the last unit of that aggregate, not the first unit of a new batch.
What is the Desiro ML Cityjet, and how do its variants differ?
The Desiro ML is Siemens’ single-deck electric multiple unit, branded Cityjet by ÖBB. Three-car sets are 75 m long with 254 regional seats; four-car sets reach about 100–101 m with 224 S-Bahn seats, while sets delivered since 2022 carry up to 290 seats.
| Variant | Formation | Length | Weight | Seats | Bicycle spaces | Typical duty |
|---|---|---|---|---|---|---|
| Regional Cityjet | 3 cars | 75 m | 145 t | 254 | 24 | REX and regional services |
| S-Bahn Cityjet | 4 cars | 100 m (ÖBB); over 101 m in Siemens’ release | 184 t | 224 | 24 | Vienna S-Bahn, six entrances per side |
| Sets delivered since 2022 | 3 or 4 cars | Up to more than 101 m | Not published per variant | Up to 290 | Up to 39 | Vorarlberg, Tyrol, Salzburg and eastern routes |
- All variants share a 160 km/h maximum speed and 2,600 kW maximum power, with level access to 550 mm platforms: ÖBB Cityjet page.
- ÖBB’s fleet list records 46 four-car and 27 three-car sets assigned to Interregio traffic, a reminder that formation length is an operational variable, not a single fleet standard: ÖBB Konzern.
- The April 2024 batch was specified with 217 seats, further optimised entrance areas, reading lights and USB ports, which shows that interior layout changed across call-offs: Siemens Mobility, 29 April 2024.
For a parts catalogue, the practical consequence is that “Desiro ML Cityjet” is not one configuration. A seat, door drive, HVAC unit or interior panel must be matched to the build standard of the specific set, and the three-car and four-car families do not share every body-side component.
Where does the fleet run, and what does it replace?
The fleet operates in all nine Austrian federal states, with the heaviest concentration in Vienna and the eastern region: S-Bahn lines such as S7 to the airport, REX regional services, the Meidling–Floridsdorf corridor and Lower Austrian branches. It added capacity; the double-deck Cityjet, not the Desiro ML, retired the Class 4020.
- Passengers first travelled on the fleet with the 2015 timetable change, initially on S7 between Vienna Floridsdorf and Vienna Airport: Siemens Mobility, 13 November 2026.
- The 21 sets ordered in 2024 were earmarked from 2026 for the Vienna Meidling–Floridsdorf main line and outer branch lines in Lower Austria: Siemens Mobility, 29 April 2024.
- The Vienna S-Bahn core line between Vienna Central Station/St. Marx and Praterstern is closed from 7 September 2026 to the end of October 2027 for the S-Bahn Wien upgrade: ÖBB closure notice.
- The Class 4020 retired in July 2026 after 48 years and 120 vehicles; the double-deck Cityjet took over its Stammstrecke role, as Bahnnews reported on 3 July 2026.
That distinction matters when suppliers describe the fleet as a replacement for older S-Bahn stock. The Desiro ML expanded single-deck capacity and took over regional and S-Bahn diagrams as it arrived, but the high-capacity double-deck Cityjet is the class that ended the 4020 era on the core line.
What does the ETCS upgrade involve, and is 2028 an official deadline?
The 2028 date is official: Siemens’ 13 November 2026 release states that the fleet is being upgraded with the latest ETCS train protection system and that completion is scheduled for 2028. The same release does not name the ETCS baseline, the on-board supplier or the retrofit contractor.
| ETCS question | Confirmed in public sources | Not disclosed |
|---|---|---|
| Scope | Fleet-wide upgrade to “the latest ETCS train protection system” | Baseline and release number |
| Completion | Scheduled for 2028 | Whether 2028 is a contractual milestone or a programme target |
| On-board equipment | Upgrade is under way | Supplier and equipment family |
| Retrofit responsibility | Not stated | Siemens, ÖBB TS or a third party |
| Earlier plan | End of 2023, per Siemens in January 2020 | Reason for the change and revised schedule |
| Trackside context | ÖBB plans ETCS Level 2 on the TEN-V core network by 2030 and the extended core by 2038 | Vehicle-track integration sequence |
- The 2028 completion date appears in both Siemens’ English release and the German release carried by OTS on 13 November 2026; the wording is “scheduled”, not “contractually committed”.
- The earlier end-2023 target is documented in Siemens’ 31 January 2020 release, which said the remaining fleet would be equipped with ETCS by the end of 2023.
- The trackside dates come from the Austrian Court of Audit’s ETCS report, which describes ÖBB Infrastructure’s 2024 strategy: core TEN-V network by the end of 2030, extended core network by 2038 (Rechnungshof report).
- Alstom’s separate ÖBB framework for up to 449 vehicles covers Railjets and locomotives with ETCS Baseline 3.6, not the Desiro ML fleet: EU ERTMS press review, August 2024. It should not be used to infer the Cityjet baseline.
Two dates are therefore in play: the vehicle retrofit completion in 2028 and the trackside roll-out that continues to 2030 and beyond. A train can carry ETCS before the route it runs on is equipped, so the two programmes do not have to finish in the same year.
Was the retrofit really about “signal spare parts”?
No. An ETCS retrofit is an on-board signalling modification — European Vital Computer, balise transmission module, odometry, driver-machine interface, radio and software — integrated with braking and traction. Spare parts are the support inventory that follows approval of the modified vehicle, not the scope of the retrofit itself.
- Siemens describes the work as upgrading the fleet with the latest ETCS train protection system, not as supplying spare components: Siemens Mobility, 13 November 2026.
- ETCS on-board equipment must be integrated with the vehicle’s braking and traction control, and the driver desk gains a new machine interface; that is an engineering change, not a consumables order.
- Once the retrofit is approved, the railway does need a spare-parts regime for the new line-replaceable units, antennas, sensors and cables. That is a downstream support task, which is why parts planning follows the retrofit rather than defining it.
The original media wording appears to have compressed “on-board signalling equipment” into “signal spare parts”. For procurement purposes the difference is material: a retrofit kit is a configuration change with documentation, testing and authorisation, while a spare part is a replacement item held against an approved configuration.
What does fleet completion change for spare-parts and maintenance planning?
Fleet completion fixes the configuration baseline: 294 sets, 898 cars, several interior layouts and lengths from 75 m to more than 101 m. Obsolescence management, modification records and pooled line-replaceable units become the main cost drivers, because every part must match a build standard and an ETCS software state.
- The fleet now spans 75 m three-car sets, 100–101 m four-car sets and later batches with up to 290 seats, so the same functional part can have several approved variants: ÖBB Cityjet page.
- The 2019 and 2020 batches were prepared for battery-hybrid conversion, a further configuration branch that affects documentation and some underfloor interfaces: Siemens Mobility, 31 January 2020.
- Long-lead electronic components remain a constraint across the sector; our 2026 lead-time review explains how to read quoted dates and avoid building a stock plan on a single distributor estimate.
- Condition monitoring is the other half of the sustainment case. The Bently Nevada spare-parts guide covers the probe, proximitor and monitor chain used on rotating machinery, including traction motors and gear units in workshop test cells.
When a fleet stops receiving new units, the build pipeline that quietly supplied spares dries up. That is the point at which a railway needs a formal obsolescence review, a last-time-buy list and a repair-versus-replace policy for each line-replaceable unit. The parts index and brand directory are the entry points for that review across Siemens, Schneider Electric, Bently Nevada and other installed bases.
How does an ETCS retrofit affect interfaces on an existing car body?
A retrofit touches antenna and balise-reader mounting, cable routes, power supply, grounding, driver-desk displays and braking interfaces, all engineered around an existing car body. Each change must be shown not to alter EMC, weight distribution or fire behaviour before the vehicle’s authorisation is extended.
- Speed and position measurement depends on robust encoders and sensors; the SICK sensors and encoders guide sets out the selection and interface points that matter when odometry hardware is replaced or added.
- The on-board radio and data links are part of the retrofit, not an afterthought. Our article on industrial network upgrades without stopping the line covers the cutover discipline that applies equally to depot and onboard networks.
- The driver-machine interface is a new display and control surface. The checks in five checks before swapping an HMI touchscreen apply to any desk display replacement, including ETCS DMI work.
- Auxiliary power and switching components around the new load must be rated for the railway environment; the Siemens SIRIUS 3RW soft starters guide explains the coordination between contactors, protection and motor loads in such cabinets.
Rail vehicle approval is a system argument, not a component argument. Adding an antenna changes the roof profile and the earthing path; adding a cabinet changes the weight distribution and the fire load; changing the DMI changes the driver’s workload and the human-machine interface assessment. The retrofit therefore has to be documented as a vehicle modification, with evidence that the existing safety case still holds.
What should buyers verify before the last unit is retrofitted?
Ask for the as-built configuration index, the approved ETCS software version, the retrofit kit’s part numbers and its obsolescence status, plus the boundary between vehicle warranty and signalling warranty. Without those four records, a spare-parts list cannot be matched to the fleet after 2028.
- Configuration control is the first check: a part number alone does not identify the approved variant if the vehicle has passed through several call-offs and one retrofit.
- Obsolescence status is the second: a retrofit kit that is already at end-of-life creates a new support problem just as the fleet enters its second decade.
- Warranty boundaries are the third: vehicle, signalling and software warranties can sit with different parties, and a failure at an interface can fall between them. The same logic applies to depot test equipment, where Schneider Modicon 140 modules are still used in test and wayside control cabinets.
The fleet is now complete, but its configuration is not static. The ETCS retrofit will create a second baseline, and the reopening of the Vienna core line in late 2027 will change how the fleet is diagrammed. Buyers who record both transitions will be able to keep spares matched to the actual fleet; those who record only the original build will be guessing by 2029.
Frequently asked questions
Does the ETCS retrofit change which Cityjet spare parts I should stock?
Yes for on-board signalling items, and no for most mechanical parts. ETCS adds or replaces line-replaceable units such as the European Vital Computer, balise antenna, odometry sensors and driver-desk hardware, and it changes software and configuration records. Mechanical parts remain governed by the build standard, but new mounting brackets, cable routes or power supplies introduced by the retrofit create new part numbers. Ask for the retrofit modification index before setting stock levels.
Can three-car and four-car Desiro ML sets cover the same diagram?
Not automatically. The three-car set is 75 m with 254 regional seats; the four-car S-Bahn set is about 100–101 m with 224 seats and six entrances per side. Platform length, stabling roads, turnround times and accessibility arrangements differ, so a substitution needs an operational check rather than a fleet-count check.
Is the 2028 ETCS completion date a contractual commitment?
Not in public sources. Siemens and ÖBB both say completion is scheduled for 2028, and neither publishes the contract terms. The earlier public target was the end of 2023, so treat 2028 as the current programme date and confirm the contractual milestone in the vehicle or signalling contract before planning depot capacity around it.
Sources
- Siemens Mobility, “ÖBB’s largest commuter and regional train fleet complete: 294 Siemens Desiro ML Cityjets now in service with ÖBB”, 13 November 2026
- Siemens Mobility, “Siemens Mobility receives order for a further 21 Desiro ML trains from ÖBB”, 29 April 2024
- Siemens Mobility, “Eleven new Desiro ML trains for ÖBB”, 31 January 2020
- OTS, “Größte Nah- und Regionalverkehrsflotte der ÖBB ist vollständig”, 13 November 2026
- ÖBB, “ÖBB Cityjet” fleet page
- ÖBB Konzern, “Personenverkehr Züge” fleet overview
- ÖBB, “Planned closures on S-Bahn Wien core line 2026/27”
- Bahnnews, “Letzte Fahrt einer Ikone: ÖBB verabschieden Baureihe 4020”, 3 July 2026
- EU ERTMS press review, “Alstom signs contract to fit ETCS on ÖBB trains”, August 2024
- Rechnungshof, “Europäisches Eisenbahnverkehrsleitsystem im ÖBB-Konzern”